TY - GEN
T1 - Collaborative Risk Management of the Approval Process of Building Envelope Materials
AU - Perrenoud, Anthony
AU - Reyes, Matt
AU - Ghosh, Somik
AU - Coetzee, Malcolm
N1 - Publisher Copyright:
© 2017 American Society of Civil Engineers.
PY - 2017
Y1 - 2017
N2 - Collaboration between owners, architects, engineers, and constructors is critical for project success; especially within alternative delivery methods such as design-build or construction management at risk. As the construction schedule is progressing and design decisions are being made, a coordinated effort is required to ensure that the finished building coincides with the owner's expectations. This paper presents a case study of the risk management efforts from a project team to ensure that the finished exterior skin of the building met project expectations. During the planning phases of the project, efforts were placed on managing project risk. Using a tool identified as a "Risk Pulse" the team identified the top risk on the project being issues with receiving the owner's approval of the building skin. The tool identified this risk as having a high likelihood of occurring with the largest impact to cost and schedule of the project. Upon identification of this risk the project team used a coordinated effort to mitigate the risk. The details of the risk management and planning processes have been captured based on observations and interviews with the participants. The paper will present the collaborative risk mitigation process used to ensure the approval of the building envelope.
AB - Collaboration between owners, architects, engineers, and constructors is critical for project success; especially within alternative delivery methods such as design-build or construction management at risk. As the construction schedule is progressing and design decisions are being made, a coordinated effort is required to ensure that the finished building coincides with the owner's expectations. This paper presents a case study of the risk management efforts from a project team to ensure that the finished exterior skin of the building met project expectations. During the planning phases of the project, efforts were placed on managing project risk. Using a tool identified as a "Risk Pulse" the team identified the top risk on the project being issues with receiving the owner's approval of the building skin. The tool identified this risk as having a high likelihood of occurring with the largest impact to cost and schedule of the project. Upon identification of this risk the project team used a coordinated effort to mitigate the risk. The details of the risk management and planning processes have been captured based on observations and interviews with the participants. The paper will present the collaborative risk mitigation process used to ensure the approval of the building envelope.
UR - http://www.scopus.com/inward/record.url?scp=85050279045&partnerID=8YFLogxK
U2 - 10.1061/9780784480502.067
DO - 10.1061/9780784480502.067
M3 - Conference contribution
AN - SCOPUS:85050279045
T3 - AEI 2017: Resilience of the Integrated Building - Proceedings of the Architectural Engineering National Conference 2017
SP - 806
EP - 816
BT - AEI 2017
A2 - Volz, Jeffery S.
T2 - Architectural Engineering National Conference 2017: Resilience of the Integrated Building, AEI 2017
Y2 - 11 April 2017 through 13 April 2017
ER -